SNP Mech
ASAŞ Alüminyum

150 MN Extrusion Press

Installation and commissioning

Press frame standing on its foundation in the extrusion hall
ASAŞ Alüminyum
Scope
Mechanical installation
Period
2025
Press force
150 MN
Discipline
Foundation · Alignment · Commissioning

Complete mechanical installation of a 150 MN extrusion press line — from foundation works, container and stem assembly, hydraulic connection and alignment through to commissioning support.

After foundation rebar, anchor placement and grouting, the press frame and table were laser aligned to manufacturer tolerance before load transfer. Alignment and levelling results were recorded and delivered with the documentation package.

The work was carried out by our own engineers and foremen alongside the equipment manufacturer's commissioning team, inside a live plant and sequenced around the client's own production and permit-to-work system.

From the site

Your next project, one team.

Share the scope of the project. We will come back to you with an engineering approach and a plan for carrying it out.

Discuss your project  →